HARDYSTON TOWNSHIP

Solar Professional Services

In an effort to reduce the Hardyston Municipal Building’s energy budget, Eneractive was contracted to perform an investigation focusing on potential solar generating activity as a solution to the problem. The solar investigation was able to yield significant results that have enabled Hardyston’s Municipal Building to reduce their energy budget and operating costs.

Specifically, Hardyston requested a photovoltaic system be studied on a carport solar support structure over the parking lot at the rear of the facility. The Eneractive team concluded that a 76.1 KWdc solar installation would be able to produce approximately 75% of the facility’s electrical requirement. Eneractive was then contracted to develop the specification for the system and provide construction management and commissioning services to facilitate the installation. The system was completed on time and for the budgeted cost and is currently producing 106% of the projected output.